Nyadi - Phidi Hydropower Project 21.4 MW
The Nyadi-Phidi hydropower project is a Run-of-River (RoR) project identified in Lamjung district of Gandaiki Province. The project utilizes discharges from both Nyadi and Phidi Rivers and its topographic head for the energy production. Two headworks are proposed to trap river water from Nyadi and Phidi River respectively. The headworks at Nyadi River lies in Jaluchhe and Bhaundanda , Marshyangdi Rural municipality at an elevation of 2948.90 masl while as secondary headworks is proposed at Phidi River at Chepebagar of Bhulbhule ,Marshyangdi rural municipality at an elevation of 3014 masl. The powerhouse of the project lies at upstream of confluence between Nyadi and Phidi River.
Name of River | Nyadi and Phidi River |
Location |
Jaluche Village – Nyadi ,Chepebagar- Phidi Marsyangdi Rural Municipility- 6 |
Type of Scheme | Run-of-River |
Installed Capacity | 21.4 MW |
Catchment Area | 67.2 Sq Km |
Head ( Gross/ Net ) | 695.66 Meter |
Design Discharge | 3.60 m3/Sec |
PPA Energy ( Yearly ) | 127.95 GWh ( Per Year ) -100% |
Dry ( Marga 16 to Jestha 15) | 40.02 GWh ( Per Year ) – 31.28 % |
Wet ( Jestha 16 to Marga 15 ) | 87.92 GWh ( Per Year ) – 68.72% |
S.No |
Task |
Status |
Remarks |
1 |
Survey License |
Obtained from Department of Electricity Development (DOED) |
8th July 2016 |
2 |
Detailed Feasibility Study |
Completed |
10th Jan 2018 |
3 |
Connection Agreement |
Completed |
6th Feb 2018 |
4 |
IEE |
Approved, Environment Ministry, Nepal |
13th April 2018 |
5 |
PPA ( with NEA) |
Signed with Nepal Electricity Authority (NEA), Nepal |
7th June 2018 |
6 |
Generation License |
Acquired from DoED, Nepal |
11th March 2019 |
7 |
Transmission Line Survey License |
Acquired from DoED, Nepal |
15th Jan 2019 |
8 |
Due Diligence Study – from Financial Institutions |
Completed, ITECO Nepal (P) Ltd |
2nd July 2019 |
9 |
Explosive Management |
Approval from Concerned Authorities |
25th Nov 2019 |
10 |
Land Lease for Project Area |
Approved from Council of Ministers- Cabinet Decision |
16th July 2019 |
11 |
Financial Closure |
Completed, Machhapuchchhre Bank |
15th Oct 2020 |
12 |
Progress of Project Access Road |
Road Construction – Ongoing at the site |
Approx. 6 km Completed |